Project Name:
|
|
|
| a.
Short name:
|
| Construction of a ceramic brick production plant |
| b.
Full name:
|
| Construction of a ceramic brick production plant with the productive capacity 30 mln conventional bricks a year on the basis of «Oranchitskoye» clay raw material deposit, Pruzhany district, Brest region |
| c.
Summary description:
|
| Production of ceramic bricks, porous hollow blocks
|
| A2.
Progress Status:
|
| Total stocks of «Oranchitskoye» deposit minerals are explored and counted up. The stocks of clays ready for commercial exploitation are handed over to the balance of PbJtStCo «Pruzhany Building Material Plant».
Laboratory and semi-factory tests are conducted for clay raw materials and thinning sand, which according to the conclusion are suitable as raw materials for production of hollow and solid face bricks of ceramic grade М 150 and higher and with the frost-resistance F 35 cycles and more, as well as ceramic porous blocks of М 75 grade with the voidage up to 50 % and minimum thermal conductivity. The manufacturing order is made for designing a walling production line. A technical and economic programme is worked out for manufacturing equipment purchases.
|
| A3.
Organizations involved and their roles:
|
| PbJtStCo «Pruzhany Building Material Plant»
225133, Pruzhany, Brest region, Kobrinskaya street, 46
Director – Kravchuk Mikhail Eugenievich, tel. +375 29 796 22 53;
(8 103751632) 92253
Chief engineer – Kalatsky Vladimir Fiodorovich, tel. +37529 8040166;
(8 103751632) 91729
fax (8 103751632) 91749, 90040,
E-mail: pksm@brest.by
|
| A4.
Project Description:
|
| Construction of a new highly asutomated ceramic face brick production plant with the productive capacity 30 mln conventional bricks a year. Planned assortment: ceramic face brick (brick dimensions - 250х120х65mm); hollow ceramic face brick with the voidage - 27% (brick dimensions - 250х120х65mm); porous ceramic block with the voidage 40÷50%, bulk density up to 1000kg/ m³, dimensions - 510х250х219(138) mm, 380х250х219 (138) mm – (slot-ridge). A plant construction site is chosen in immediate proximity to Oranchitsy railway station and is situated 7,5 km from the deposit.
|
| a.
Project cost (mln USD):
|
| 22.275 |
| A5.
Background / history / overall programme / related or similar projects:
|
| In 2007-2008 the clay raw materials and thinning sand of the Northern part of «Oranchitskoye» clay raw material deposit, Pruzhany district, Brest region were explored in detail. The total stocks of explored and counted up minerals make up 32 mln. m³. The stocks of clays ready for commercial exploitation are handed over to the balance of PbJtStCo «Pruzhany Building Material Plant» make up 1955 thousand m³ and 231 thousand m³ of thinning sand, which will ensure operation of a plant with the productive capacity 30 mln. pieces during 27 years.
|
| A6.
Environmental impact summary:
|
| No negative environmental impact.
|
| A7.
Possible obstacles/ problems/ risk assessment:
|
|
|
| A8.
Term of realization / term of recoupment:
|
| 2 / 7,1 (8)
|
| A9.
Project’s branch:
|
| Building industry
|
|
| B1. Project physical components |
B2. Capital cost (mln USD) |
| pre-investment outlay |
0.675 |
| building and assembly works |
8.1 |
| equipment acquisition and assembling |
13.5 |
| TOTAL: |
22.275 |
|
|
|
|
|
|
|
|
| |
| B3. Sub-projects by location |
B4. Project cost (mln USD) |
|
|
|
|
|
|
|
|
|
| C1. Resources 'in kind', grants, investments, equity / ownership, etc. |
C2. Amount (mln USD) |
|
|
|
|
|
|
|
|
|
|
|
|
|
| D1.
Financing gaps, type of financial assistance required:
|
| Investments
|
| D2. Sources of finance |
D3. Type of investment |
D4. Amount (mln USD) |
| Foreign investment funds: |
Direct foreign investments |
22.275 |
|
|
|
|
|
|
|
|
|
| D5.
Financial/ International Institution Name:
|
|
|
|
| E1.
Type of users/ markets, volumes, pricing, revenues, quantifiable benefits/ savings:
|
| a) demand volume – 144 180 thousand dollars USA
b) main consumers: specialised construction organizations of various forms of ownership that make investments into reconstruction, modernization of production; people who carry out construction
c) estimated product sales amount – 9 77 thousand dollars USA
. d) net discounted profit – thousand dollars USA
е) intrinsic norm of yield – 7 %
g) yield index - 1,16
|
| E2. Revenues (Sales) |
E3. Amount (mln USD) |
| estimated product sales amount |
9.77 |
|
|
|
|
|
|
|
|
|
| F1.
Cost components, strategies for cost recovery, operating organisations, subsidies, etc.:
|
| Taxes and dues
Production and sale costs
|
| F2. Cost Item |
F3. Amount (mln USD) |
| material costs, including:
- fuel-energy resources;
- raw stuff and materials
|
2.39 |
| remuneration of labour expenses |
0.594 |
| assessments to social needs |
0.208 |
| amortisation |
0.945 |
| other |
0.142 |
|
|
|
|
|
|
|
|
|
| G1. Net Income Value |
G2. Amount (mln USD): |
| Net profit after payments |
3.219 |
| Net income (net profit + amortisation) |
4.166 |
|
|
|
|
|
|
|
| H1.
This form was completed by:
|
| Kalatsky Vladimir Fiodorovich, chief engineer
|
| H2.
Organisation (address):
|
| PbJtStCo «Pruzhany Building Material Plant» 225133, Pruzhany, Brest region, Kobrinskaya street,46
|
| H3.
Tel/Fax/E-mail:
|
| fax (8 103751632) 91749, 90040, тел. +37529 8040166; (8 103751632) 91729 E-mail:pksm@brest.by
|
| H4.
Date:
|
| October, 2011
|
| H5.
H5. Supreme Organization:
|
| Brest Region Executive Committee
|
|
|