| Русская версия |
|
| A1.
Project Name:
|
|
|
| a.
Short name:
|
| Construction of Nemnovskaya HPS |
| b.
Full name:
|
| Construction of Nemnovskaya hydro power station on the river Neman |
| c.
Summary description:
|
| Construction of hydro power station on the river Neman |
| A2.
Progress Status:
|
| Feasibility study is developed.
|
| A3.
Organizations involved and their roles:
|
| 1) RUP «Belnipienergoprom» – development 2) State Production Unit «Belenergo» (RUP «Grodnoenergo») – implementation 3) Coordinator - Ministry of Energy of the Republic of Belarus (contact person: Ekaterina Rybakova, ph. 375 17 2182145, em: rybakova@min.energo.net.by
|
| A4.
Project Description:
|
| The project involves: construction of the flood plain power plant with closed machine hall, ferro-concrete water discharge dam with flat section shutters for dropping flood waters; a one-chamber shipping slues for shipping in summer.
The station will provide the following characteristics: installed capacity – 19,8 MW, note of normal support level – 94m; number of turbines – 5, number of generators – 5. To transmit the electric power produced into energy consuming system the open switchgear with two 16 MV.A transformers and 110 kV gas-insulated breakers in the closed type building with 6 kV switchgear will be constructed.
The approximate date of the beginning of the construction – 2012; financing: direct investment.
Delivery of the equipment: Austria, Checks Republic, Switzerland, China.
|
| a.
Project cost (mln USD):
|
| 139.0 |
| A5.
Background / history / overall programme / related or similar projects:
|
| The facility RUP «Grodnoenergo» was established in 1963. It involves Grodno heat power station HPS-2, Lidskaya HPS, Severnaya mini-HPS in Grodno, oblast and regional heat and electric networks. Electric power installed is 208.5 MW. The length of heat network is
457 km, the length of electric network is more than 37 thousand km.
|
| A6.
Environmental impact summary:
|
| There is some impact, but without harmful emissions.
|
| A7.
Possible obstacles/ problems/ risk assessment:
|
| Good grade of stability
|
| A8.
Term of realization / term of recoupment:
|
| 4 / 27
|
| A9.
Project’s branch:
|
| Electric energy
|
|
| B1. Project physical components |
B2. Capital cost (mln USD) |
| Equipment (Austria, Checks Republic, Switzerland, China) + construction works |
139.0 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
| B3. Sub-projects by location |
B4. Project cost (mln USD) |
|
|
|
|
|
|
|
|
|
| C1. Resources 'in kind', grants, investments, equity / ownership, etc. |
C2. Amount (mln USD) |
|
|
|
|
|
|
|
|
|
|
|
|
|
| D1.
Financing gaps, type of financial assistance required:
|
| Foreign investment
|
| D2. Sources of finance |
D3. Type of investment |
D4. Amount (mln USD) |
| Foreign investment funds: |
Project financing, direct investment |
139.0 |
|
|
|
|
|
|
|
|
|
| D5.
Financial/ International Institution Name:
|
|
|
|
| E1.
Type of users/ markets, volumes, pricing, revenues, quantifiable benefits/ savings:
|
| Production of electric power by use of the river Neman water recourses to cover partially the load of Grodno power unit
|
| E2. Revenues (Sales) |
E3. Amount (mln USD) |
| Depends on acting tariffs for energy |
|
|
|
|
|
|
|
|
|
|
| F1.
Cost components, strategies for cost recovery, operating organisations, subsidies, etc.:
|
|
|
| F2. Cost Item |
F3. Amount (mln USD) |
| Heat, water, amortization, labor cost, taxes, etc |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| G1. Net Income Value |
G2. Amount (mln USD): |
|
|
|
|
|
|
|
|
|
|
|
| H1.
This form was completed by:
|
| Vitaly Sobko, Head of Strategy Department
|
| H2.
Organisation (address):
|
| SPU «Belenergo», 14, K. Marx str., Minsk, 220030, Republic of Belarus
|
| H3.
Tel/Fax/E-mail:
|
| Tel.: +375 17 2182043, fax: +375 17 2182639; e-mail: sobko@bel.energo.net.by
|
| H4.
Date:
|
| December, 2011
|
| H5.
H5. Supreme Organization:
|
| Ministry of Energy of the Republic of Belarus
|
|
|