| Русская версия |
|
| A1.
Project Name:
|
|
|
| a.
Short name:
|
| Construction of Zelvenskaya CES |
| b.
Full name:
|
| Construction of 920 MW Coal Condensation Electric Power Station Zelvenskaya |
| c.
Summary description:
|
| Construction of new coal electric power station at the site to the south of the settlement Zelva in Grodno district at the distance of 110 km from Grodno and 45 km from Poland |
| A2.
Progress Status:
|
| Feasibility study is in progress. Coal market is under investigation
|
| A3.
Organizations involved and their roles:
|
| 1) RUP «Belnipienergoprom» – development 2) State Production Unit «Belenergo» (RUP «Grodnoenergo») – implementation
3) Ministry of Energy of the Republic of Belarus - сoordinator
|
| A4.
Project Description:
|
| Construction of 920 MW coal condensation electric power station with the installation of two 460 MW units. The unit involves stem turbine K-330-23,5 and steam dust coal boiler for super critical steam parameters.
|
| a.
Project cost (mln USD):
|
| 1311 |
| A5.
Background / history / overall programme / related or similar projects:
|
| The facility RUP «Grodnoenergo» was established in 1963. It involves Grodno heat power station, oblast and regional heat and electric networks. Electric power installed is 184.5 MW. The length of heat network is 475 km, the length of electric network is more than 37 thousand km.
|
| A6.
Environmental impact summary:
|
| No assessment
|
| A7.
Possible obstacles/ problems/ risk assessment:
|
| Good grade of stability
|
| A8.
Term of realization / term of recoupment:
|
| -/ 12
|
| A9.
Project’s branch:
|
| Electric energy
|
|
| B1. Project physical components |
B2. Capital cost (mln USD) |
| Equipment (Germany, Sweden, Russia, Ukraine) + construction works |
1311 |
| Total: |
1311 |
|
|
|
|
|
|
|
|
|
|
|
|
| |
| B3. Sub-projects by location |
B4. Project cost (mln USD) |
|
|
|
|
|
|
|
|
|
| C1. Resources 'in kind', grants, investments, equity / ownership, etc. |
C2. Amount (mln USD) |
|
|
|
|
|
|
|
|
|
|
|
|
|
| D1.
Financing gaps, type of financial assistance required:
|
| Foreign direct investment
|
| D2. Sources of finance |
D3. Type of investment |
D4. Amount (mln USD) |
| Foreign investment funds: |
Direct investment |
1311 |
|
|
|
|
|
|
|
|
|
| D5.
Financial/ International Institution Name:
|
| Not available
|
|
| E1.
Type of users/ markets, volumes, pricing, revenues, quantifiable benefits/ savings:
|
| Electric supply of industrial enterprises and population in the premises of the power station
|
| E2. Revenues (Sales) |
E3. Amount (mln USD) |
|
|
|
|
|
|
|
|
|
|
|
| F1.
Cost components, strategies for cost recovery, operating organisations, subsidies, etc.:
|
|
|
| F2. Cost Item |
F3. Amount (mln USD) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| G1. Net Income Value |
G2. Amount (mln USD): |
|
|
|
|
|
|
|
|
|
|
|
| H1.
This form was completed by:
|
| Vitaly Sobko, Head of Strategy Department
|
| H2.
Organisation (address):
|
| SPU «Belenergo», 14, K. Marx str., Minsk, 220030, Republic of Belarus
|
| H3.
Tel/Fax/E-mail:
|
| Tel.: +375-17-2182043, fax: +375-17-2182639; e-mail: sobko@bel.energo.net.by
|
| H4.
Date:
|
| December, 2011
|
| H5.
H5. Supreme Organization:
|
| Ministry of Energy of the Republic of Belarus
|
|
|